The Road Conservation Executing Unit (Covial) reported that, by the installation of the Second bridge in it stretch of the kilometer 11.5 of the route to El Salvadorit will be necessary to close the step.
The step in km 11.5 will be closed from May 3 to 5 by the installation of beams. (PHOTO FREE PRESS: CIV)
He Ministry of Communications, Infrastructure and Housing (CIV) indicated this April 25 that close the step at kilometer 11.5 of the aforementioned roadto continue with the repair of the stretch affected by sinking.
This is the Second structure meaningful Guatemala City to the Eastwhere they will be installed longitudinal beams And, as a precaution, It will restrict mobility.
The closure will be made from the Saturday, May 3 at 10:00 p.m. to him Monday, May 5 at 4.00 hours.
In case of concluding the work before the planned time, the transit will be immediately enabledthe institution added.
The CIV reported that personnel from the General Directorate of Protection and Road Safety (Provincial) and of the Municipal Traffic Police of Santa Catarina Pinula They will coordinate the closures vehicular and the Step through alternate roads.
The authorities have indicated that the Route to Muxbal It can be one of the alternatives For drivers.