The Ministry of Communications announces closure at kilometer 11.5 of the route to El Salvador for works in the central section of the second bridge.
CIV announces jobs at km 11.5 of the route to El Salvador. (Free Press Photo: CIV video capture)
The Ministry of Communications, Infrastructure and Housing (CIV) reported that from June 7 to 9 will carry out the road closure at kilometer 11.5 of the Route to El Salvadorfor works in the central section of the second bridge.
He added that the closure will begin on Saturday, June 7 at 10:00 p.m. and will end on Monday 9 at 4.00 hours.
He indicated that, in recent months, the works have shown advances that have allowed the final phase of execution.
He explained that, in the second bridge under construction, divided into three sections, the installation of longitudinal beams is pending in the central section. These, due to their weight and dimensions, require the use of cranes and heavy machinery, which need a wide maneuvering space to operate effectively and safely.
According to the CIV, the General Directorate of Road Protection and Safety and the Municipal Police of Traffic of Santa Catarina Pinula will support the road closure. They will also collaborate in the regulation of traffic on alternate routes.
To conclude the work before planned, the step will be enabled immediately, said the CIV.
He added that it is requested to avoid circulating through the area; If it is extremely necessary, use alternate routes, exit in advance and be attentive to the indications of the road agents and the official information, which will be published in a timely manner.