First section between zones 2 and 6 will be enabled

Home News First section between zones 2 and 6 will be enabled
First section between zones 2 and 6 will be enabled

For Saturday, June 21, the official authorization of the section that includes from 12 “A” avenue in zone 2 to 16 avenue in Zone 6, as part of the works carried out by the Municipality of Guatemala on Martí Street, is planned.

According to the information provided by the capital commune, this first section has been completed, which goes from The 12 avenue “A” until 16 avenue, in the immediate vicinity of the Santa Cruz del Milagro parish, zone 6.

This first phase includes 560 meters of roads, distributed in two lanes. Two layers of asphalt were applied: a base of 14 cm conventional asphalt mixture and a 7 cm of modified asphalt mixture, on a stabilized base of 30 cm.

In the next stage it will continue towards the blade in zone 6. This section is approximately 920 meters long, in three lanes and subsequently, it will continue towards the Belize bridge. Then, it will be the turn of the entrance lane to the city according to the projections of the commune.

The municipality includes the placement of 34 thousand square meters again asphalt throughout the road, which will represent a substantial improvement in the entire route where more than 150 thousand vehicles are estimated daily.

Related readings


Related readings


A month of jobs at Martí

The works for the repair and authorization of this important route began on May 17 and, according to the estimates of the Municipality of Guatemala, the work is expected throughout Martí street, as well as on the José Milla and Vidaurre roadconclude in a period not exceeding six months.

According to estimates of the capital commune, the project for repairing the asphalt tape in both arteries will cost more than Q40 million and will benefit approximately 580 thousand people who travel daily through the area.

The works cover in their entirety a section of 1,980 linear meters and an area of ​​34 thousand 180 square meters. In this, the complete replacement of the asphalt is carried out, deteriorated by the constant passage of light vehicles and heavy transport, mainly trucks that transport merchandise to the Atlantic and the departments of the East and northeast of the country, as well as those that come from these localities and that, when they reach the city, move along Martí street and the José Milla and Vidaurre road, which they connect directly to the peripheral ring, which directly connects to the peripheral ring, the south of the capital and also in the opposite direction.

Martí street and the José Milla and Vidaurre road They connect zones 1, 2, 6, 17, 18, 24 and 25, in addition to serving the municipalities of San Pedro Ayampuc, Chinautla, Palencia and other surrounding areas. Therefore, the authorities consider that the works are of great importance to expedite traffic, especially in peak hours.

Project phases

The information provided by The capital commune indicates that the work is carried out in several phasesranging from the 12 avenue “A” in zone 2 to the beginning of the Belize bridge that connects with the route to the Atlantic:

  • First phase: 485 linear meters will be intervened, from the 12th “A” avenue, zone 2, to 15 avenue, zone 6
  • Second phase: It includes 920 meters, from 14 avenue to 21 avenue, zone 6
  • Third phase: It covers the section from 21 avenue to the beginning of the Belize bridge

It is expected that the works can be completed before the end of this year, according to estimates of the capital commune.