These works will be carried out in Zone 9

Home Business These works will be carried out in Zone 9
These works will be carried out in Zone 9

The construction of Guatemala City AeroMetro entered a new stage. After completing the placement of structural towers in the area of ​​the Montúfar Streetfrom May 11 will begin phase 4 of 7corresponding to the electromechanical work in two stations that correspond to the Line 1.

This phase will cover the section where the stations are located Spain Square and Tecún Umánstrategic points of the initial route between Plaza España and El Trébol.

The seasons 1 Plaza España and 2 Tecún Umánlocated on the Montúfar Streetwill be the first on Line 1 of the Aerometer in advancing to phase 4 of 7corresponding to the electromechanical works starting May 11. (Photo, Prensa Libre: courtesy Fundesa)

Preliminary work in Plaza España

Victor Peralta, director of Mikasa Groupa company in charge of electromechanical assembly, reported that this Saturday May 9 Preliminary work will begin on the Plaza España Station, located in zone 9.

The maneuvers will begin at 4amwith the transfer of a crane, counterweights and tool containers from the storage area located in the Major Seminary, Mixcowhere it will also be the Center West.

Upon arrival at the site, personnel will carry out stabilization, assembly and configuration of the crane, followed by technical tests and safety reviews before beginning assembly.

During the afternoon, the first two platforms with materials from the electromechanical system will also be received, with the aim of starting formal work on Monday, May 11 at 7 am

New road closures on Calle Montúfar

For the beginning of this new stage, during the week a new reduction of lanes was reported on the Montúfar Streetas part of the work linked to the project.

The authorities reported that it remains vehicle restriction in the 12 Montúfar street and 0 avenue, zone 9where only the center lane remains enabled.

In order to reduce congestion, drivers were recommended to use the following alternative routes:

  • Connection to La Castellana avenue
  • Access to Liberation Boulevard

This is how Line 1 of the AeroMetro progresses

The Line 1 contemplates four seasons and will connect Plaza España with El Trébol. The current progress is as follows:

  • Plaza España Station: Located on Montúfar Street. The electromechanical phase (4/7) will begin on May 11.
  • Tecún Umán Station: It already has the installation of structural towers. It is expected to continue with phase 4 after the work in Plaza España.
  • CAMIP station: It remains in phase 2 of 7.
  • Clover Station 1: Continues in phase 2 of 7.

According to information shared by the development company, each station will have approximately 10 meters wide.

Technical plan shows the dimensions and scope of the crane that will be used in the electromechanical works at the Plaza España and Tecún Umán stations, as part of the progress of the AeroMetro project on Montúfar Street. (Photo, Prensa Libre: courtesy CableVía)
Technical plan shows the dimensions and scope of the crane that will be used in the electromechanical works at the Plaza España and Tecún Umán stations, as part of the progress of the AeroMetro project on Montúfar Street. (Photo, Prensa Libre: courtesy CableVía)

The seven construction phases of the AeroMetro

Previously, the Municipality of Guatemala has shared that the project contemplates seven main stages that are:

  1. Foundation construction
  1. Placement of structural bases
  1. Tower installation
  1. Electromechanical works
  1. Station construction
  1. Wiring voltage
  1. Cabin installation

Currently, the phase 4 It will be executed only in two stations on Line 1 located on Montúfar Street.

RELATED READINGS

Each AeroMetro cabin will have capacity for 12 seated passengers and will have security cameras, direct communication systems and panic buttons for users. (Photo, Prensa Libre: courtesy)
chevron-right

AeroMetro routes, stations and fares

The cabins will have capacity for 10 to 12 passengersair conditioning and panoramic windows. The system will operate approximately 17 hours a day.

Route 1: Plaza España – El Trébol

  • Four seasons:
    • Spain Square
    • Tecún Umán
    • CAMIP
    • Clover 1

Route 2: El Trébol – Roosevelt Causeway

  • Seven seasons:
    • Clover 1
    • Roosevelt Hospital
    • Kaminal Juyú-Mirador-RusMall
    • Utatlan
    • Saint Rita
    • Cotó Scale
    • Flower Mill

Integration with lines of the TransMetro (L7, L12 and L13)bike lanes and Express Mixco buses.

Map of the AeroMetro route shows its two routes and the 11 planned stations, which will connect Plaza España, El Trébol and Calzada Roosevelt at the height of Molino de las Flores. (Photo, Prensa Libre: courtesy Municipality of Guatemala)
Map of the route of the Aerometer shows its two paths and the 11 stations projected, which will connect Spain Square, The Clover and the Roosevelt Causeway at the height of Molino de las Flores. (Photo, Prensa Libre: courtesy Municipality of Guatemala)

Estimated construction and operation time

The total construction of both lines is projected to be completed within a maximum period of 30 monthsafter having formally started in November 2025.

If the established deadlines are met, the Aerometer could begin gradual operations in the 2027starting with the Line 1after passing technical tests and international certifications.