Thousands of rural Guatemalan families are one step closer to switching on a light bulb. The board of the National Electrification Institute (INDE) approved on November 11 the award of an international tender worth Q215.2 million for rural electrification works, financed with part of a loan from the Inter-American Development Bank (IDB), Prensa Libre reported.
Who gets power
The project is split into three lots and is expected to reach between 10,000 and 12,000 homes in 133 communities. Contractors have 10 months from the start order to deliver the works.
- Lot 1: 46 communities — 31 in Cobán, Alta Verapaz; 13 in Nentón and two in Cuilco, Huehuetenango.
- Lot 2: 47 communities in Alta Verapaz: Raxruhá (13), San Pedro Carchá (21) and Fray Bartolomé de las Casas (3).
- Lot 3: 40 communities — 23 in Cobán and six in San Juan Chamelco, Alta Verapaz; six in Chicamán, Quiché; and five in Rabinal, Baja Verapaz.
Who won
Two bids were received on July 1, according to the Guatecompras procurement system. The winning offer, Q215,213,024.40, came from a joint venture of Importadora de Materiales Eléctricos (Impelsa), Representaciones CEM, Proase and Prefabricados Cifa. The other bidder, Ingenieros en Mantenimiento Aplicado, offered Q174.6 million, but only for two of the three lots. INDE said the totals were not directly comparable because they covered different scopes, and that the evaluation considered the scope of works, not just the headline amount.
Second attempt
This was the second try. The first tender, launched in August 2025, drew a single bidder and was declared void on March 13, 2026. The works belong to the Rural Electrification Infrastructure Program (PIER), backed by a US$120 million loan approved by Congress through Decree 23-2025 and financed half by the IDB and half by Korean cooperation. The program as a whole aims to bring electricity to 40,000 homes.
INDE also holds a second IDB loan, for US$250 million, for the Rural Electrification Access Program (PAER). Lawmakers have questioned the institute this year over slow execution of both credits, so the pace of the new works will be closely watched in the communities still waiting for the grid.