The CIV has reported on the status of the Palín-Secla highway and gave a new date for the conclusion of the repair works.

SECTION-PROVISIONAL-EN-RUTA-PALIN-ESCUINTLA_7BF8D1

Damage to the Palín – Escuintla highway generates impact on the mobility of heavy transport, so business sectors have requested the CIV to expedite repairs. (Photo: PL hemeroteca)

This February 27 the authorities ofl Ministry of Communications, Infrastructure and Housing (CIV) They updated the state of the works that are carried out on the Palín-Secuintla route.

During a press conference made Thursday, Minister Miguel Ángel Díaz Bobadilla said that the progress of the work in the Kilometer 39, 44 and 45 of the route are at 75% completed.

The minister said that at the end of March this year the work on the route would be concluding, in addition to asserting that The four lanes of the section will operate correctly.

“We have been constantly monitoring the advance of the works even at night“Bobadilla said.

Read more: Civ announces the total closure of the passage through km 44 of the Palín-Escuintla highway

With respect to the road sections that are found judicialized, the minister said that he has to follow “what the Layo stipulates.”

“We can’t do anything else and we are Waiting for the corresponding judicies to be resolved“said the minister.

The works at kilometer 44 of the Palín-Squintla highway They continue after last June 13, 2024 a sinking will be recorded.

Source