Guatemala’s first highway built under a public-private partnership (PPP) is nearly ready to open, but drivers will have to wait. Operator Convía says the Escuintla–Puerto Quetzal highway is in the handover phase, with technical and legal reviews under way and no date yet for toll collection, Prensa Libre reported.
Where things stand
Sandro Testelli, Convía’s country director, said the project is wrapping up its first stage, known as phase A, and that the company met the agreed delivery date of Nov. 11. Since then, files have been under review by the Ministry of Communications, Infrastructure and Housing (CIV), as the state owns the road, and by the National Infrastructure Agency (ANI), which checks contractual compliance.
“Everyone’s concern is to finish this process in an orderly way and set a date, in coordination with the authorities, to start operating,” Testelli said. Tests are being carried out daily on different parts of the work.
Two new disputes
Delivery was originally planned for July but was rescheduled to Nov. 11 after negotiations in the first half of the year. Now a fourth and fifth dispute have been triggered between the parties. Details are covered by a confidentiality clause, and meetings are under way to reach a solution. Between January and June 2026 the project had already faced three disputes that led to contract changes.
The PPP contract allows adjustments through arbitration and conciliation mechanisms. Prensa Libre said it asked the CIV and ANI for comment; both were still to respond at the time of publication.
On the ground
During a visit by Prensa Libre and Guatevisión, work crews were still active on the main sections, building toll booths in both directions and installing road signs.
Why it matters
The highway links Escuintla with Puerto Quetzal, the country’s main Pacific port, a key route for exports and imports. How smoothly the handover goes will be watched closely as a test case for future PPP projects in Guatemala.
What to watch
Three things will define the coming weeks: whether the CIV and ANI sign off on the files, how the two new disputes are resolved under the contract, and when the authorities announce the start of operations and the toll schedule for drivers and cargo trucks heading to the port.